July
2008 Update:
On
July 16, 2008, three panel Members were appointed to a
joint federal-provincial panel established to review the
proposed Dunvegan Hydroelectric Project. The
establishment of the Joint Panel is the result of some
complicated legal issues related to recent case law that
has unfortunately affected this Project at a very late
stage.
While disappointed that the Project is being subjected
to this level of review, Canadian Hydro has always been
willing to go above and beyond when it comes to
environmental assessment and review. We will continue to
work through this process and are optimistic the
collaborative work of employees, consultants and the
local community, along with the diligent oversight of
provincial and federal regulators over the past decade,
will result in approval of the Dunvegan Hydroelectric
Project by the Joint Panel.
Now
that the Joint Panel is appointed, they have up to 45
days to either determine sufficiency of the evidentiary
record, or request additional information on the
Project. Once the Panel determines evidentiary
sufficiency, it has to give a minimum 30 days notice of
hearing. Following the close of the hearing, the Panel
has 90 days to issue its decision.
Construction is expected to occur over four years and
generate approximately 500 person-years of employment.
Construction could commence as early as next spring if
the hearing and related approvals proceed in a timely
manner.
The
proposed Dunvegan Hydroelectric Project is an
environmentally responsible, low-impact development of
the hydroelectric potential of the Peace River. The
project is based on a world-class renewable energy
resource that will be a 100-year asset for the community
and province, and demonstrates Canadian Hydro’s
commitment to the sustainable development of northern
energy resources.
The
Project will feature innovative fish passageways for
upstream and downstream migrating fish and has also
resulted in the creation of a state-of-the-art ice model
that is specific to the Peace River.
Canadian Hydro is extremely pleased with the strong
local support and will continue to work with local
communities and stakeholders, as we have done over the
last decade, to ensure concerns are identified and
effectively addressed.
Background Information on the Joint Panel
A
joint panel agreement between the Government of Canada,
the Natural Resources Conservation Board (NRCB) and the
Alberta Utilities Commission (AUC) is now released after
receiving public comments in early May 2008. It
describes the process for conducting the joint panel
review and details on the scope of the environmental
assessment.
The
joint panel agreement, biographical information on the
panel members along with more information on this
project are available on the Web sites of the Canadian
Environmental Assessment Agency Registry number
04-05-2996, the NRCB and the AUC.
March 2008 Update:
On January 25, 2008, Glacier Power Ltd. received notice that
Mr. Mike Boyd, a Director under the Alberta
Environmental Protection and Enhancement Act (EPEA),
had advised the Natural Resources Conservation Board (NRCB)
that the Environmental Impact Assessment, submitted in
2006 in support of the Dunvegan Hydroelectric Project
application, had been deemed complete pursuant to
Section 53 of the EPEA.
On January 28, 2008, the Alberta Energy and Utilities Board
and NRCB (together, the Boards) held a pre-hearing
meeting regarding the Dunvegan Hydroelectric Project.
The purpose of the pre-hearing meeting was to allow
those interested in participating in a public hearing to
identify themselves and make submissions outlining their
position(s) with respect to the proposed Project, and
outline preferences in terms of the scope, location, and
timing of the formal hearing. Glacier Power was also
given the opportunity to express its position on the
topics identified by the interested parties, and
requested that a hearing be held as soon as possible, in
Fairview, Alberta.
The result of the pre-hearing meeting was a decision by the
Boards to hold a focused public hearing in Fairview,
Alberta, scheduled to commence on April 22nd,
2008 and run no longer than the 25th of
April. However, on March 19th, 2008, Glacier
Power Ltd. and other interested parties received notice
from the NRCB that in order to assist with the
fulfillment of federal legal requirements, the federal
government had requested that the Boards postpone the
April 22nd hearing. In the spirit of the
Canada-Alberta Agreement on Environmental Assessment
Cooperation, the Boards agreed to post-pone the
hearing. Glacier Power Ltd. is still awaiting
clarification on the nature of the referenced federal
legal requirements, and will provide additional
information on the re-scheduled hearing as it becomes
available.
The pre-hearing decision report and information regarding
hearing postponement can be found on the NRCB website
at:
http://www.nrcb.gov.ab.ca/nrp/Currentapplications.aspx?id=3544.
December 2007
On November 13th, 2007, Glacier Power Ltd.
filed its response to the 234 questions included in the
Supplemental Information Request (SIR) for the proposed
Dunvegan Hydro Project (the Project). The questions were
received in July 2007 from the Natural Resources
Conservation Board on behalf of all involved regulatory
agencies, provincial and federal, based on their review
of the Environmental Impact Assessment (EIA) submitted
in November 2006. Electronic and hard copies of the
completed document were distributed, not only to
regulatory agencies, but to all other interested parties
who initially received or requested a copy of the EIA.
Anyone else who is interested in seeing the SIR
response document can access the information
here, at
Alberta Environment (AENV) offices near the Project
site, as well as town and municipal offices near the
Project site.
Glacier Power Ltd. is
hopeful that, with the SIR response document filed, it
will be possible to enter the next phase of the
regulatory approval process quickly. Glacier Power Ltd.
expects the next phase of the process to consist of a
pre-hearing, and potentially a full public hearing, both
of which would be administered and presided over by
members of the Natural Resources Conservation Board and
the Alberta Energy and Utilities Board. This phase
involves ongoing consultation with stakeholders.
Interested parties are encouraged to contact Glacier
Power Ltd. with any questions regarding the Project or
regulatory process.
October 2007
Since the previous
update in March of this year, one significant milestone
has been achieved in that the various regulatory
agencies charged with reviewing the proposed Dunvegan
Project EIA have completed their initial review. The
result of that review is a set of questions referred to
as the Supplemental Information Request (SIR) that was
provided to Glacier Power Ltd. on July 17th. July is a
number of months later than was anticipated for EIA
review completion and delivery of the SIR in the
schedule originally provided by Alberta Environment (AENV).
The SIR contains
numerous questions that relate to the information
provided in the EIA, as well as requests for additional
information that was not included in the EIA. Some of
the questions are very technical in nature and require
additional work by Glacier Power’s various experts and
scientists, and others are simply a matter of editing.
Glacier Power’s goal is to provide the SIR response to
regulators in early October. By doing so, Glacier Power
hopes to get back on schedule and complete the EIA
process along the timelines originally presented by AENV.
Glacier Power is
working closely with the departments who posed the
questions, as well as their own consultants to ensure
the SIRs are answered clearly and completely.
Representatives for the majority of departments
reviewing the EIA attended a sight tour with
representatives from Glacier Power in an effort to
ensure a full understanding the proposed Project. When
the response to the SIRs is complete and has been
submitted to regulators, the information will be
publicly available through various AENV offices, as well
as on this website.
Another development
since the last update was provided is that the public
response to the joint notice mentioned in the previous
update resulted in Glacier Power receiving five
statements of concern (SOCs). SOCs are letters submitted
by members of the public who have concerns regarding
potential impacts from the Project and would like them
considered in reference to the proposed development.
Glacier Power Ltd. is currently working with each of the
groups who submitted SOCs to address all of the concerns
raised.
March 2007
Applications for the Dunvegan Hydroelectric Project were
submitted to Alberta Environment, the Natural Resources
Conservation Board, and the Alberta Energy and Utilities
Board in November
2006.
An Environmental
Impact Assessment (EIA) Report was submitted in support
of the applications. The final EIA Document can be
downloaded from the
Document Library.
Submission of these applications and the Environmental
Impact Assessment Report triggered a formal regulatory
review process. At the beginning of March 2007
public notice of
the
application for the Dunvegan Hydroelectric Project was
jointly published by
Alberta
Environment, the Natural Resources Conservation Board,
and the Alberta Energy and Utilities Board in several
Alberta newspapers. A copy of the Joint Notice
can be seen by clicking
here. The notice provides contact
information for those wanting to file statements of
interest or concern with Alberta Environment, and sets a
deadline of April 26, 2007 for the submission of those
statements. The notice provides further
instruction on how to register withe Boards to receive
notices respecting the review process.
February 2007
Public Information Sessions
- Dunvegan Environmental Impact Assessment
See your local newspaper or
click
below
for more details
-
Open House Feb 20-22 (Fairview, Peace River, Spirit
River)
-
Open House Feb 27 (Tangent)