| |
Southern Alberta Wind Plants
Southern Alberta Wind Plants Brochure
 |
|
A Golden Moment at the Cowley North Wind Plant |
Canadian Hydro operates three wind plants in southwestern Alberta
near the town of Pincher Creek: Cowley Ridge, Cowley North and
Sinnott.
As this area is nestled against the Rocky Mountains, this is an
ideal site for wind technology. Warm Chinook winds run down the
eastern slopes of the Rocky Mountains and turn the rotors of the
giant wind turbines. From there, wind energy enters Alberta’s
electrical grid, which powers homes and businesses throughout
Alberta.
Cowley Ridge
The Cowley Ridge Wind Plant is the first commercial wind plant in
Canada. Phase One was commissioned in 1993 and Phase Two in 1994.
Easily seen off Highway #3 from the Town of Cowley, the Cowley
Ridge Wind Plant features 57 Kenetech turbines, with a total
capacity of 21.4 megawatts. Average production from this wind plant
is more than 60 million kilowatt hours of electricity per year,
which is enough to power 8,400 typical Canadian households.
The wind turbines at Cowley Ridge are mounted on 24.5 metre
lattice towers and operate at wind speeds of up to 97 kilometres per
hour. Each turbine has three blades and rotors that are 33 metres in
diameter. Approximately two hours of production from one
Kenetech turbine powers a typical Canadian home for one
month.
Cowley North & Sinnott
The Cowley North Wind Plant is located directly north of Cowley
Ridge and became operational starting in September 2001. There are
fifteen Nordex N60 turbines, each with a potential to produce 1.3
megawatts. Operational starting in December 2001, the Sinnott Wind Plant is
directly east of Cowley Ridge. This wind plant has five Nordex N60
turbines in test locations.
When compared to the turbines at Cowley Ridge, each new turbine at
the Cowley North and Sinnott Wind Plants is twice the
physical size with the capacity for 3.5 times the power output.
With a rotor diameter of 60 metres, the new turbines can operate at
wind speeds of up to 90 kilometres per hour.
The Nordex N60 turbine flying only approximately 35 minutes
generates enough electricity to power a typical home for a month.
Canadian Hydro expects these two new plants to generate 70,000
megawatt hours per year.
Taylor Wind Plant
In the fall of 2004, 9 Kenetech
375 kW wind turbines were installed on the
hill above the 13 MW
Taylor hydro facility, which is located south of Magrath,
Alberta. Reconditioning and installation of the Kenetech
turbines was conducted by Canadian Hydro staff.
This installation takes advantage of the existing grid connection,
which will now be used on a year-round basis. With the hydro
facility, the grid connection was previously used from April to
September.
Soderglen Wind
Plant
In March 2007, Canadian Hydro acquired 50% ownership of the
Soderglen Wind Plant. This facility is located in southern Alberta
approximately 20 kilometers southwest of Fort Macleod. Commercially
operational in September 2006, the Soderglen Wind Plant consists of
47, GE 1.5 MW SLE wind turbines.
Southern Ontario Wind Plant
Melancthon Brochure
Melancthon I
Canadian Hydro owns and operates 45 turbines at the
Melancthon I Wind Plant near Shelburne, Ontario. Residents of
Melancthon Township can vouch that regular, strong wind is a feature
of this area, which makes it particularly suitable for the
installation of a wind plant. The electricity from these turbines
enters the Ontario electrical grid, which powers homes, schools,
hospitals and businesses throughout Ontario.
After only nine months of construction Canadian Hydro
achieved commercial operation of the Melancthon I Wind Plant on
March 4, 2006. It takes teamwork, passion, and above all,
perseverance from a team of stakeholders to move low-impact
renewable energy projects forward from concept to completion.
The team of stakeholders included the local community, landowners, employees
and directors, engineers, contractors, suppliers, as well as ongoing
support from the federal, provincial and municipal governments.
Some of the notable economic contributions to Melancthon
Township include award of contracts to 25 local area companies, with
a total value of $16 million. There are nine new full time
operating and managerial positions associated with the Melancthon I
Wind Plant and ongoing maintenance contracts are awarded for a range
of services. The Melancthon Wind Plant is a low‑impact development
that allows agricultural land to remain in its rural state and
farmers can plant crops right up to the base of the turbines.
Cattle can graze right below the turbines and wildlife continues to
flourish.
Quebec Wind Plant
Le Nordais Wind Plant
In December
2007, Canadian Hydro acquired the Le Nordais Wind Plant for a total
cost of $121 million. Located on the Gaspé Peninsula, it consists of
131 NEG-Micon turbines, which generate an average of 165,000
MWh/year. The plant has been operating since 1999. The acquisition
included the existing long-term power purchase agreement (PPA) with
Hydro-Quebec.
|